Installation and Start-Up150kW InfraStruXureTM SystemLarge Data Centers480 V/ 600V Input
2 150kW InfraStruXure System—Installation and Start-Up WarningsReceiving/movingDo not tilt the PDU greater than 45° from its vertical axis. Never lay
Safety: Warnings150kW InfraStruXure System—Installation and Start-Up 3Total Power Off1. Set the PDU Main Input to OFF.2. Set the upstream power sourc
Safety: Warnings4 150kW InfraStruXure System—Installation and Start-Up EMIThis equipment has been tested and found to comply with the limits for Class
150kW InfraStruXure System—Installation and Start-Up 5Site PlanningDimensionsInfraStruXure PDUNetShelter VX Enclosure81in (2060mm)7.2in(183mm)Without
6 150kW InfraStruXure System—Installation and Start-Up Space ConsiderationsStudy the figure below to determine your space requirements for installing
150kW InfraStruXure System—Installation and Start-Up 7Weight ConsiderationsEnsure that the floor and sub-floor can support the total weight of the co
8 150kW InfraStruXure System—Installation and Start-Up Heat Output Consider the heat dissipation ratings of equipment to determine cooling requirement
150kW InfraStruXure System—Installation and Start-Up 9Electrical Requirements and SpecificationsProcedures requiring a licensed electricianElectrical
10 150kW InfraStruXure System—Installation and Start-Up Emergency Power Off (EPO)OverviewTo provide a mechanism for emergency power off, attach a remo
150kW InfraStruXure System—Installation and Start-Up 11Basic Installation ProcedureThis section provides the basic steps that you need to perform whe
208/480/600V
Site Planning: Basic Installation Procedure12 150kW InfraStruXure System—Installation and Start-Up 8. Install Shielding Troughs, Shielding Partitions,
150kW InfraStruXure System—Installation and Start-Up 13Installation ProceduresLevel the PDU and NetShelter EnclosuresLeveling feet are attached under
14 150kW InfraStruXure System—Installation and Start-UpConnect the Power Source to the PDUAccess the PDU Main Input breakerOpen the back doors of the
Installation Procedures: Connect the Power Source to the PDU150kW InfraStruXure System—Installation and Start-Up 15– In the top of the PDU for overhea
Installation Procedures: Connect the Power Source to the PDU16 150kW InfraStruXure System—Installation and Start-UpRoute the input conductors to the M
150kW InfraStruXure System—Installation and Start-Up 17Connect an Emergency Power Off SwitchOverviewConnecting the switch. The Emergency Power Off (EP
Installation Procedures: Connect an Emergency Power Off Switch18 150kW InfraStruXure System—Installation and Start-UpConnect an EPO switch to the user
Installation Procedures: Connect an Emergency Power Off Switch150kW InfraStruXure System—Installation and Start-Up 193. Test the EPO switch to ensure
Installation Procedures: Connect an Emergency Power Off Switch20 150kW InfraStruXure System—Installation and Start-UpSafety warningsHazardous voltage
150kW InfraStruXure System—Installation and Start-Up 21Connect User Input Contacts and Relay Outputs to the User Connection PlateOverviewMake contact
150kW InfraStruXure System—Installation and Start-Up iAbout this Manual This manual is intended for APC Field Service Engineers or APC-trained install
Installation Procedures: Connect User Input Contacts and Relay Outputs to the User Connection Plate22 150kW InfraStruXure System—Installation and Star
150kW InfraStruXure System—Installation and Start-Up 23Install Shielding Troughs, Shielding Partitions, and Cable LaddersShielding Troughs and Shieldi
Installation Procedures: Install Shielding Troughs, Shielding Partitions, and Cable Ladders24 150kW InfraStruXure System—Installation and Start-UpShie
150kW InfraStruXure System—Installation and Start-Up 25Install InfraStruXure Rack-Mount DevicesInstall the Rack Automatic Transfer Switches (ATS)Insta
26 150kW InfraStruXure System—Installation and Start-UpRoute and Attach Overhead WiringRoute and attach power cables to equipment racksIf you ordered
Installation Procedures: Route and Attach Overhead Wiring150kW InfraStruXure System—Installation and Start-Up 27– For dual feed devices within a redun
Installation Procedures: Route and Attach Overhead Wiring28 150kW InfraStruXure System—Installation and Start-Up5. From each NetShelter VX Enclosure,
150kW InfraStruXure System—Installation and Start-Up 29Wiring Under the FloorIf you are routing power cables to the enclosures under a raised floor, y
Installation Procedures: Wiring Under the Floor30 150kW InfraStruXure System—Installation and Start-Up5. At the circuit breaker panel, cut the wires t
150kW InfraStruXure System—Installation and Start-Up 31Route Data Cables to the InfraStruXure Manager Hub (or Switch)1. Connect a Cat-5 network cable
150kW InfraStruXure System—Installation and Start-Up 33Start-Up ProcedureSafety warningsThis section provides instructions on how to perform a system
Start-Up Procedure34 150kW InfraStruXure System—Installation and Start-Up3. Set the Main Output circuit breaker on the front of the PDU to OFF.
Start-Up Procedure150kW InfraStruXure System—Installation and Start-Up 35Apply power to the system1. Set the upstream input circuit breaker (utility o
Start-Up Procedure36 150kW InfraStruXure System—Installation and Start-Up4. Set the Main Output circuit breaker on the PDU to ON. 5. Close (turn ON) t
150kW InfraStruXure System—Installation and Start-Up 37Configure the InfraStruXure ManagerOnce all equipment is installed, the network cables are conn
150kW InfraStruXure System—Installation and Start-Up 39Appendix A: OperationHow to Apply Power to the SystemThis procedure instructs on how to apply p
Appendix A: Operation40 150kW InfraStruXure System—Installation and Start-Upb. Close (turn ON) the PDU distribution panel circuit breakers.NoteWhen th
150kW InfraStruXure System—Installation and Start-Up 41How to Ensure Total Power Off1. Open (turn OFF) the main circuit breaker on the power source fe
Contents150kW InfraStruXure System—Installation and Start-Up iiiSafety ...1Overview
Index150kW InfraStruXure System—Installation and Start-Up 43AApplying power to the system 33–34, 37–38Automatic transfer switches, installing 25CCabl
44 150kW InfraStruXure System—Installation and Start-Up UUpdates, to this manual iWWarnings 2–4Wiring, under the floor 29
*990-1983*APC Worldwide Customer SupportCustomer support for this or any other APC product is available at no charge in any of the following ways:• Vi
iv 150kW InfraStruXure System—Installation and Start-Up Installation Procedures ... 13Level the PDU and NetShel
150kW InfraStruXure System—Installation and Start-Up vStart-Up Procedure ...31Safety warnings . . . .
150kW InfraStruXure System—Installation and Start-Up 1Safety OverviewSave these instructionsThis manual contains important instructions that must be