Page 1 - Installation and Start-Up

Installation and Start-Up150kW InfraStruXureTM SystemLarge Data Centers480 V/ 600V Input

Page 2 - 208/480/600V

2 150kW InfraStruXure System—Installation and Start-Up WarningsReceiving/movingDo not tilt the PDU greater than 45° from its vertical axis. Never lay

Page 3 - About this Manual

Safety: Warnings150kW InfraStruXure System—Installation and Start-Up 3Total Power Off1. Set the PDU Main Input to OFF.2. Set the upstream power sourc

Page 4

Safety: Warnings4 150kW InfraStruXure System—Installation and Start-Up EMIThis equipment has been tested and found to comply with the limits for Class

Page 5 - Contents

150kW InfraStruXure System—Installation and Start-Up 5Site PlanningDimensionsInfraStruXure PDUNetShelter VX Enclosure81in (2060mm)7.2in(183mm)Without

Page 6

6 150kW InfraStruXure System—Installation and Start-Up Space ConsiderationsStudy the figure below to determine your space requirements for installing

Page 7

150kW InfraStruXure System—Installation and Start-Up 7Weight ConsiderationsEnsure that the floor and sub-floor can support the total weight of the co

Page 8

8 150kW InfraStruXure System—Installation and Start-Up Heat Output Consider the heat dissipation ratings of equipment to determine cooling requirement

Page 9

150kW InfraStruXure System—Installation and Start-Up 9Electrical Requirements and SpecificationsProcedures requiring a licensed electricianElectrical

Page 10 - Warnings

10 150kW InfraStruXure System—Installation and Start-Up Emergency Power Off (EPO)OverviewTo provide a mechanism for emergency power off, attach a remo

Page 11 - Emergency Power Off (EPO)

150kW InfraStruXure System—Installation and Start-Up 11Basic Installation ProcedureThis section provides the basic steps that you need to perform whe

Page 13 - Site Planning

Site Planning: Basic Installation Procedure12 150kW InfraStruXure System—Installation and Start-Up 8. Install Shielding Troughs, Shielding Partitions,

Page 14 - Space Considerations

150kW InfraStruXure System—Installation and Start-Up 13Installation ProceduresLevel the PDU and NetShelter EnclosuresLeveling feet are attached under

Page 15 - Weight Considerations

14 150kW InfraStruXure System—Installation and Start-UpConnect the Power Source to the PDUAccess the PDU Main Input breakerOpen the back doors of the

Page 16 - Heat Output

Installation Procedures: Connect the Power Source to the PDU150kW InfraStruXure System—Installation and Start-Up 15– In the top of the PDU for overhea

Page 17 - Electrical requirements

Installation Procedures: Connect the Power Source to the PDU16 150kW InfraStruXure System—Installation and Start-UpRoute the input conductors to the M

Page 18

150kW InfraStruXure System—Installation and Start-Up 17Connect an Emergency Power Off SwitchOverviewConnecting the switch. The Emergency Power Off (EP

Page 19 - Basic Installation Procedure

Installation Procedures: Connect an Emergency Power Off Switch18 150kW InfraStruXure System—Installation and Start-UpConnect an EPO switch to the user

Page 20 - See also

Installation Procedures: Connect an Emergency Power Off Switch150kW InfraStruXure System—Installation and Start-Up 193. Test the EPO switch to ensure

Page 21 - Installation Procedures

Installation Procedures: Connect an Emergency Power Off Switch20 150kW InfraStruXure System—Installation and Start-UpSafety warningsHazardous voltage

Page 22

150kW InfraStruXure System—Installation and Start-Up 21Connect User Input Contacts and Relay Outputs to the User Connection PlateOverviewMake contact

Page 23 - Install a circuit breaker

150kW InfraStruXure System—Installation and Start-Up iAbout this Manual This manual is intended for APC Field Service Engineers or APC-trained install

Page 24 - Terminal Torque Tools

Installation Procedures: Connect User Input Contacts and Relay Outputs to the User Connection Plate22 150kW InfraStruXure System—Installation and Star

Page 25 - Overview

150kW InfraStruXure System—Installation and Start-Up 23Install Shielding Troughs, Shielding Partitions, and Cable LaddersShielding Troughs and Shieldi

Page 26 - Normally ClosedNormally Open

Installation Procedures: Install Shielding Troughs, Shielding Partitions, and Cable Ladders24 150kW InfraStruXure System—Installation and Start-UpShie

Page 27 - Active Alarm xxofxx

150kW InfraStruXure System—Installation and Start-Up 25Install InfraStruXure Rack-Mount DevicesInstall the Rack Automatic Transfer Switches (ATS)Insta

Page 28 - Safety warnings

26 150kW InfraStruXure System—Installation and Start-UpRoute and Attach Overhead WiringRoute and attach power cables to equipment racksIf you ordered

Page 29

Installation Procedures: Route and Attach Overhead Wiring150kW InfraStruXure System—Installation and Start-Up 27– For dual feed devices within a redun

Page 30

Installation Procedures: Route and Attach Overhead Wiring28 150kW InfraStruXure System—Installation and Start-Up5. From each NetShelter VX Enclosure,

Page 31 - Partitions, and Cable Ladders

150kW InfraStruXure System—Installation and Start-Up 29Wiring Under the FloorIf you are routing power cables to the enclosures under a raised floor, y

Page 32

Installation Procedures: Wiring Under the Floor30 150kW InfraStruXure System—Installation and Start-Up5. At the circuit breaker panel, cut the wires t

Page 33

150kW InfraStruXure System—Installation and Start-Up 31Route Data Cables to the InfraStruXure Manager Hub (or Switch)1. Connect a Cat-5 network cable

Page 36

150kW InfraStruXure System—Installation and Start-Up 33Start-Up ProcedureSafety warningsThis section provides instructions on how to perform a system

Page 37 - Wiring Under the Floor

Start-Up Procedure34 150kW InfraStruXure System—Installation and Start-Up3. Set the Main Output circuit breaker on the front of the PDU to OFF.

Page 38 - Terminal Torque Too ls

Start-Up Procedure150kW InfraStruXure System—Installation and Start-Up 35Apply power to the system1. Set the upstream input circuit breaker (utility o

Page 39 - Manager Hub (or Switch)

Start-Up Procedure36 150kW InfraStruXure System—Installation and Start-Up4. Set the Main Output circuit breaker on the PDU to ON. 5. Close (turn ON) t

Page 40

150kW InfraStruXure System—Installation and Start-Up 37Configure the InfraStruXure ManagerOnce all equipment is installed, the network cables are conn

Page 42

150kW InfraStruXure System—Installation and Start-Up 39Appendix A: OperationHow to Apply Power to the SystemThis procedure instructs on how to apply p

Page 43 - Apply power to the system

Appendix A: Operation40 150kW InfraStruXure System—Installation and Start-Upb. Close (turn ON) the PDU distribution panel circuit breakers.NoteWhen th

Page 44

150kW InfraStruXure System—Installation and Start-Up 41How to Ensure Total Power Off1. Open (turn OFF) the main circuit breaker on the power source fe

Page 45

Contents150kW InfraStruXure System—Installation and Start-Up iiiSafety ...1Overview

Page 47 - Appendix A: Operation

Index150kW InfraStruXure System—Installation and Start-Up 43AApplying power to the system 33–34, 37–38Automatic transfer switches, installing 25CCabl

Page 48

44 150kW InfraStruXure System—Installation and Start-Up UUpdates, to this manual iWWarnings 2–4Wiring, under the floor 29

Page 50

*990-1983*APC Worldwide Customer SupportCustomer support for this or any other APC product is available at no charge in any of the following ways:• Vi

Page 51

iv 150kW InfraStruXure System—Installation and Start-Up Installation Procedures ... 13Level the PDU and NetShel

Page 52 - Wiring, under the floor 29

150kW InfraStruXure System—Installation and Start-Up vStart-Up Procedure ...31Safety warnings . . . .

Page 54 - *990-1983*

150kW InfraStruXure System—Installation and Start-Up 1Safety OverviewSave these instructionsThis manual contains important instructions that must be